Reference — Section 09

Timeline & Next Steps

Fourteen weeks, overlapping on purpose. And what we would need in week one.

Master Schedule

Stages overlap because a boutique team cannot dedicate itself to one stage at a time

W1–2W3–4W5–6W7–8 W9–10W11–12W13–14
S0 — Foundation
W1–3
S1 — Knowledge Base
W2–5
S2 — Safety Net
W4–8
S3 — Pilot
W7–11
S4 — Measure & Refine
W10–12
S5 — Rollout
W11–14
S6 — Continuous
W13+

What each stage needs from the one before it

S0 Foundation baseline S1 Knowledge patterns S2 Safety net HARD GATE S3 Pilot evidence S4 Measure GO / NO-GO S5 → S6 Rollout, then run Skip the baseline here and no later claim can be defended Net must exist before generation at volume Real gate. “Stop” is an allowed answer Overlap is intentional. If a stage's entry criteria are not met, we move the next stage — not the criteria.
StageWeeksThe one thing that must come outGate to proceed
S0 Foundation1–3Signed baseline including the seven-band time splitBaseline agreed in writing by both sides
S1 Knowledge Base2–5Patterns file, domain glossary and module docs reviewed by their ownersContradictions in the codebase resolved and written down
S2 Safety Net4–8Enforced CI gate, characterization coverage, golden datasets frozenSuite green and gating. Agents replay-validated
S3 Pilot7–11One change end to end, one non-owner change, one restricted-zone changeFull metric set captured against the baseline
S4 Measure10–12Per-agent verdicts and a joint, documented rollout decisionEvidence supports scaling. A real gate
S5 Rollout11–14All modules onboarded. Internal maintainers trainedRunbooks handed over. Stewards named
S6 Continuous13 onNamed duties with a cadence, owned entirely by you—

Staffing Assumptions

Stated because the schedule depends on them, and we do not have your headcount yet

These are assumptions. Tell us where they are wrong.

The 14 weeks assume one pilot squad. If n.tasc is maintained by three people, the stages stretch and we would propose a leaner fleet in a different order. If it is twenty across several squads, Stage 5 parallelises and rollout compresses. The sequence holds either way. Only the duration changes.

RoleAssumed commitmentHeaviest weeks
Tech lead / architectAbout half time across the programmeW1–5 (audit, patterns), W10–12 (verdicts)
Backend engineers (2)About a quarter time to W6, then full pilot participationW7–11
UI engineer (1)About a quarter time, mostly in the pilotW9–11
QA engineer (1)About half time, rising through Stage 2W4–11
Domain owner(s)2–3 days per golden-dataset scenario familyW4–7 — the hardest commitment to protect
DBAOccasional, for schema and migration reviewW4–8
Product / BAAbout a quarter time for spec reviewW7–11
ConceptGood consultantEmbedded throughoutFull programme

What We Need in Week One

Nothing here needs a commitment beyond the engagement itself

Repository and pipeline access

Read access to the n.tasc codebase, plus sight of the current build configuration. Read-only is enough for all of Stage 0.

Delivery history

Last 20 completed changes and last six months of defects. This is where the baseline and the seven-band time split come from.

An hour with the module owners

The conventions and quirks that are not written down anywhere. Scans find structure. Only people know intent.

Named domain owners

The people who can say whether a business-critical figure is right. They own the restricted gate for the life of the programme.

Schema access

Schema only, never production data. Enough to inventory where business logic lives in the database.

A view on the client contracts

Does any of them constrain AI-assisted development or require disclosure? Better in week one than month four.

A candidate pilot module

Real client-requested work, outside the deepest restricted zone, crossing backend / React UI / database, with a steward who wants it to work.

Answers to the open questions

The Assumptions section lists what this plan assumes. Correcting those is the fastest way to sharpen the schedule and the fleet.

Where we start on day one

The baseline. Pulling the last 20 changes apart into the seven bands tells us which agents matter most for you rather than in general — and it is the number every later claim gets measured against.